• Courses
  • Job Seekers
  • Employers
 

Resume : 338508 Shortlist  |   |  Print

Mechanical Inspector ( Static/Rotating Equipments

Preparation, review and approval of documents about Inspection Test Plan of the project to ensure inspection shall be in accordance with the required Quality Standard and Procedures. Execute and develop quality audit of Sub-contractors inspection documentation works for Static and Rotating Equipments to assure that the required forms used in testing submitted are approved by client representative.Regular surveillance checking at site to ensure that all comments had appropriate corrective action

Work Preferences

Desired Salary
75,000 - 85,000 per year  
Availability
Immediately  
Desired Job Type
Contract  
Can Travel for Work
A Lot  
Highest Education Level
Bachelor Degree  
Current Location
WA - Other  
Willing to relocate?
Yes
Residency / Visa
I require sponsorship

Skills Profile

Construction
Inspectors
Technical Skills Skill Last Used Yrs. Exp.  
  Auto CAD Release 10 1994 2  
  Microsoft Excel 2011 13  
  Microsoft Words 2011 13  

Employment History

Job Title
QA/QC Mechanical Inspector ( Static/Rotating Equipments )
Industry
Oil and Gas
07/2008 to 05/2010

Preparation, review and approval of documents about InspectionTest Plan of the project to ensure inspection shall be in accordance with the requiredQuality Standard and Procedures.

Execute and develop quality audit of Sub-contractorsinspection documentation works for Static and Rotating Equipments to assurethat the required forms used in testing submitted are approved by clientrepresentative as per ITP such as:

-        Installation checklist for static/rotatingequipments

-        Leveling / alignment recording forms forhorizontal, vertical, package type

-        Axial/radial, soft foot, parallelism forms forpumps and compressors.

Regular surveillance checking at site to ensure thatall comments had appropriate corrective action such as:

-        Verify the preservation requirements foranchor bolts during construction stage.

-        Check the physical condition of anchor boltsand leveling of foundations before erection of equipments.

-        Check preservation status of equipments atsite and storage area to ensure the requirements of client and vendor are donesuch as rust prevention to equipment especially offshore area, monitor thenitrogen purging requirements for vessels and compressors, rotation ofshafting, oil filling and cleaning of equipments.

-        Verify all materials which required for indoorand outdoor storage.

-        Ensure to have a preservation log for all theequipments checked and monitor daily / weekly for easily tracking the status.

-        Confirm that all instruments used foralignment and leveling by subcontractor are calibrated with stickers indicatedthe date of calibration and re-calibration.

-        Verify the erection of equipments such ascompressors, drivers, diesel equipments, vessels and other equipment if theyfollow the Method of Statement.

-        Check the shimming requirements forstatic/rotating equipments. 

-        Check and monitor the grouting preparation ofall equipments ready for grouting and verify the preparation requirements suchas pre-watering of foundation, chipping, cleaning and form works requirements.

-        Ensure that inspection areas are safe forworking with required level of safety.

-        Verify condition of axial/radial withoutpiping prior for preparation for piping installation.

-        Verify piping support and test acceptanceprior for final alignment.

Follow up implementation of corrective actionregarding quality issues on the project.

Settle effective procedures for the satisfactoryperformance of the work in accordance with quality control and inspection testplan.

Routine inspection of construction activities ofStatic / Rotating equipment and HVAC works step by step to ensure that therequirements in the drawing and specification are met and that all the worksare carried out in good workmanship.

Perform inspection with the vendor and clientrepresentative to demonstrate or shown compliance with the requirements duringfabrication and construction stage such as:

-        Check Static / Rotating and HVAC equipmentarrive at site shall have each equipment tag number and name plate. Visualinspection for any damage cause during transportation. Dimensional inspectionas per design order.

-        Verify the release note of civil about foundationready preparation for alignment and leveling. Checked setting of padding plates,sole plates or mounting plates and verify the elevation and coordinates for X –Y axis preparation for erection. Checked anchor bolt projection and anchor boltcentering as per equipment requirements.

-        Check equipment orientation before and aftererection.

-        Witness the leveling / verticality checking ofhorizontal and vertical equipment prior for grouting and for piping erection.Verification of anchor bolt tightening prior for grouting. Issue a release noteto civil and piping respectively after alignment / leveling and verify againthe anchor bolt final tightening.

-        Preliminary alignment of rotating equipmentssuch as pumps, compressors, gear box, turbine, blowers, diesel engine andothers. Check the soft foot of motors shimming condition. Check the axial /radial alignment (angular alignment) or shaft alignment @ cold condition usingdial gauge or laser equipment. Check the distance shaft ends (DBSE) @ coldcondition and pre stretch especially for rotating equipments with gearbox. Checkthe skid leveling in regards to base of motors and pumps. Check the anchor bolttightening of skid prior for grouting, piping installation to suction anddischarge.

-        Verify the parallelism on suction / discharge pipingconnection if stress free condition. Checked before and after suction anddischarge pipe are assembled to pump or compressor.

-        Internal inspection of vessels horizontal / verticalequipments and check the internal attachment required such as demister, trays(odd / even trays) valve caps, down comer plate, filter cartridge, distributorsand others. Check internal cleanliness of vertical and horizontal vessel priorfor equipment temporary or final box-up. Verify the final gasket to beinstalled during final box-up.

-        Checked external attachment such as platforms,ladders, support and instruments are installed and inspected.

Reviewed Method of Statement prepared bysubcontractors regarding construction activities that will guide them to ConstructionActivities.

Provide early warning of potential quality problemof Static/Rotating and HVAC equipments during fabrication and installation.

Support contractor to maximum extent, possible tomake contractor successful.

Input contractor’s daily accomplishment aboutconstruction and inspection activities of Static/Rotating and HVAC equipments.

Coordinate and engage the support services ofengineering and vendors for some cases encountered at fabrication / site whichrequired their immediate decision and action. 

Job Title
QA/QC Mechanical Inspector ( Static/Rotating Equipments )
Industry
Oil and Gas
08/2007 to 05/2008

Preparation, review and approval of documents about InspectionTest Plan of the project to ensure inspection shall be in accordance with the requiredQuality Standard and Procedures.

Execute and develop quality audit of Sub-contractorsinspection documentation works for Static and Rotating Equipments to assurethat the required forms used in testing submitted are approved by clientrepresentative as per ITP such as:

-        Installation checklist for static/rotatingequipments

-        Leveling / alignment recording forms forhorizontal, vertical, package type

-        Axial/radial, soft foot, parallelism forms forpumps and compressors.

Regular surveillance checking at site to ensure thatall comments had appropriate corrective action such as:

-        Verify the preservation requirements foranchor bolts during construction stage.

-        Check the physical condition of anchor boltsand leveling of foundations before erection of equipments.

-        Check preservation status of equipments atsite and storage area to ensure the requirements of client and vendor are donesuch as rust prevention to equipment especially offshore area, monitor thenitrogen purging requirements for vessels and compressors, rotation ofshafting, oil filling and cleaning of equipments.

-        Verify all materials which required for indoorand outdoor storage.

-        Ensure to have a preservation log for all theequipments checked and monitor daily / weekly for easily tracking the status.

-        Confirm that all instruments used foralignment and leveling by subcontractor are calibrated with stickers indicatedthe date of calibration and re-calibration.

-        Verify the erection of equipments such ascompressors, drivers, diesel equipments, vessels and other equipment if theyfollow the Method of Statement.

-        Check the shimming requirements forstatic/rotating equipments. 

-        Check and monitor the grouting preparation ofall equipments ready for grouting and verify the preparation requirements suchas pre-watering of foundation, chipping, cleaning and form works requirements.

-        Ensure that inspection areas are safe forworking with required level of safety.

-        Verify condition of axial/radial withoutpiping prior for preparation for piping installation.

-        Verify piping support and test acceptanceprior for final alignment.

Follow up implementation of corrective actionregarding quality issues on the project.

Settle effective procedures for the satisfactoryperformance of the work in accordance with quality control and inspection testplan.

Routine inspection of construction activities ofStatic / Rotating equipment and HVAC works step by step to ensure that therequirements in the drawing and specification are met and that all the worksare carried out in good workmanship.

Perform inspection with the vendor and clientrepresentative to demonstrate or shown compliance with the requirements duringfabrication and construction stage such as:

-        Check Static / Rotating and HVAC equipmentarrive at site shall have each equipment tag number and name plate. Visualinspection for any damage cause during transportation. Dimensional inspectionas per design order.

-        Verify the release note of civil about foundationready preparation for alignment and leveling. Checked setting of padding plates,sole plates or mounting plates and verify the elevation and coordinates for X –Y axis preparation for erection. Checked anchor bolt projection and anchor boltcentering as per equipment requirements.

-        Check equipment orientation before and aftererection.

-        Witness the leveling / verticality checking ofhorizontal and vertical equipment prior for grouting and for piping erection.Verification of anchor bolt tightening prior for grouting. Issue a release noteto civil and piping respectively after alignment / leveling and verify againthe anchor bolt final tightening.

-        Preliminary alignment of rotating equipmentssuch as pumps, compressors, gear box, turbine, blowers, diesel engine andothers. Check the soft foot of motors shimming condition. Check the axial /radial alignment (angular alignment) or shaft alignment @ cold condition usingdial gauge or laser equipment. Check the distance shaft ends (DBSE) @ coldcondition and pre stretch especially for rotating equipments with gearbox. Checkthe skid leveling in regards to base of motors and pumps. Check the anchor bolttightening of skid prior for grouting, piping installation to suction anddischarge.

-        Verify the parallelism on suction / discharge pipingconnection if stress free condition. Checked before and after suction anddischarge pipe are assembled to pump or compressor.

-        Internal inspection of vessels horizontal / verticalequipments and check the internal attachment required such as demister, trays(odd / even trays) valve caps, down comer plate, filter cartridge, distributorsand others. Check internal cleanliness of vertical and horizontal vessel priorfor equipment temporary or final box-up. Verify the final gasket to beinstalled during final box-up.

-        Checked external attachment such as platforms,ladders, support and instruments are installed and inspected.

Reviewed Method of Statement prepared bysubcontractors regarding construction activities that will guide them to ConstructionActivities.

Provide early warning of potential quality problemof Static/Rotating and HVAC equipments during fabrication and installation.

Support contractor to maximum extent, possible tomake contractor successful.

Input contractor’s daily accomplishment aboutconstruction and inspection activities of Static/Rotating and HVAC equipments.

Coordinate and engage the support services ofengineering and vendors for some cases encountered at fabrication / site whichrequired their immediate decision and action. 

Qualifications

Completed Institution Degree / Qualification
1976 Tinurik Elementary School Graduated Elementary Education  
1980 Tanauan Institute Graduated High School Education  
1987 Technological Institute of the Philippines Bachelor of Science in Mechanical Engineering